Rear Elevation of House and Garage


Good view of basement walkout, main floor and second floors. House and garage will eventually be attached. Exterior siding is complete on this side of the house and will be painted.

Siding Prep and installation



Two views of the exterior siding. Note the shingle style at the top. Siding will be painted later.

Front Porch



Front porch will wrap around three sides of the front elevation.

Front Elevations April 2008


View from the top of the drive way. Note the sign "Lone Pine Tree Ranch." Garage completely framed.

Great Room Interior


View from middle of the great room looking toward the front entry. Coat closet and stairs on right. Above is the second floor crossover. It will have railing toward the greatroom. Opposite wall is one wall of the second floor bathroom.

Great Room Interior


This view is from middle of great room looking west or toward the rear of the house. Beams have been sealed recently.

Interior Photos


Bay window ready to go in the dining area.

Garage Walls



March 24-26, 2008 garage walls on first floor up and starting on the second floor.

Roof Prep


First stages of prep for cold roof.

Garage



Concrete gets final smooth finish.

Garage



Two views of the concrete pour of the main floor of the garage.

Garage


Main floor of garage ready for concrete pour.